Boost for Jaitapur n-project: 61 pc opt for new land compensation deal

JaitapurThe Jaitapur Nuclear Power Project has picked pace with 61 per cent of the project affected persons accepting the additional land compensation package of Rs 22.5 lakh per hectare since March this year.

The Jaitapur Nuclear Power Project (JNPP) has picked pace with 61 per cent of the project affected persons (PAPs) accepting the additional land compensation package of Rs 22.5 lakh per hectare since March this year.

According to Sandeep Singhroy, director, JNPP, of the total 2,336 khatedars or land title holders, 1,484 have collected the land compensation cheques so far. While the figure stood at less than 300 PAPs till March this year, it saw a sharp increase after the state government approved the additional ex-gratia payment of Rs 22.5 lakh per hectare in February this year, as recommended by a state government-appointed committee based on market rates. Of the 1,484 who have opted for the compensation, 1,423 have taken the ex-gratia payment so far.

"The numbers are increasing by the week. There is a general encouragement among the people after the announcement of the ex-gratia amount and the progress of accepting cheques is satisfactory," Singhroy said.

The ex-gratia amount of Rs 22.5 lakh per hectare is reported to be more than 80 times the original amount. While land for the project was acquired at different rates, NPCIL sources said the initial payments were as low as Rs 25,000 per hectare.

The land acquisition amount was earlier fixed at Rs 14.77 crore as per the Land Acquisition Act. But the NPCIL has now earmarked an additional Rs 211 crore as ex-gratia payment, following the panel's recommendations.

A total of 938.026 hectares (692.311 hectares for the plant site and 245.715 hectares for the residential complex) has been acquired for the project. The state government handed over possession of the land to the NPCIL in 2010.

The rehabilitation package agreement, signed between the state government and NPCIL in October 2010, also requires NPCIL to provide Rs 2 crore per village for civic amenities and Rs 25 lakh per village per year for maintenance. The maintenance amount will be increased by 10 per cent every three years.

... contd.

Please read our terms of use before posting comments
TERMS OF USE: The views, opinions and comments posted are your, and are not endorsed by this website. You shall be solely responsible for the comment posted here. The website reserves the right to delete, reject, or otherwise remove any views, opinions and comments posted or part thereof. You shall ensure that the comment is not inflammatory, abusive, derogatory, defamatory &/or obscene, or contain pornographic matter and/or does not constitute hate mail, or violate privacy of any person (s) or breach confidentiality or otherwise is illegal, immoral or contrary to public policy. Nor should it contain anything infringing copyright &/or intellectual property rights of any person(s).