DVC expects to commission Purulia power plant in March

Damodar Valley Corporation (DVC) expects to commission the first unit of Ragunathpur thermal power unit in Purulia district by March next year, an official said on Sunday. "The initial date for commissioning of the first unit was in November 2010, but due to non-availability of water we could not start the unit," chief engineer of Ragunathpur Thermal Power Station (RTPS) J K Singh told reporters.

However, he said recently the water connectivity work has begun for a 10-km pipeline from Panchet dam to the plant site.

The project has been delayed by 18 months due to problems in land acquisition. The second unit of the fist phase is expected to be commissioned in the middle of 2013, Singh said. The first phase of the thermal power project consists of two units of 600 MW each.

Please read our terms of use before posting comments
TERMS OF USE: The views expressed in comments published on indianexpress.com are those of the comment writer's alone. They do not represent the views or opinions of The Indian Express Group or its staff. Comments are automatically posted live; however, indianexpress.com reserves the right to take it down at any time. We also reserve the right not to publish comments that are abusive, obscene, inflammatory, derogatory or defamatory.