FE@CAMPUS MASTERMIND: Response by Ravi Shah to question for Jan 14-20

Fe camous

Response to question for Jan 14-20: WILL INVESTMENT IN INDIA PICK UP ONCE ENVIRONMENTAL CLEARANCES START COMING THROUGH?

Yes, I believe Investments in India will pick up once environmental clearances start coming through.

The environmental clearance process is required for 39 types of projects and covers aspects like screening and evaluation of the upcoming project.

Industrial projects located in any of the following notified ecologically fragile/sensitive areas would require environmental clearance irrespective of the type of project:

Religious and historic places

Archaeological monuments

Scenic areas

Hill resorts

Beach resorts

Coastal areas rich in mangroves, corals, breeding grounds of specific species

Estuaries

Gulf areas

Biosphere reserves

National parks and sanctuaries

National lakes and swamps

Seismic zones

Tribal settlements

Areas of scientific and geological interest

Defence installations, specially those of security importance and sensitive to pollution

Border areas (international)

Airports

This coupled with delays occurring because of unsatisfactory administrative arrangements, in place, to support the procedure for granting or refusing clearances is slowing the growth of India and scaring away investors.

In a recent debate on this issue our PM remarked that the Forest Conservation Act had emerged as the new "licence-permit-quota raj".

In a recent situation cited by the Finance Ministry regarding a power project, it stated that a power project requires coal linkages. The ministry of power consulted the ministry of coal. Since coal linkage requires environmental clearances, the coal ministry passed the buck to the MoEF.

Sometimes, the department of forests points to the National Wild Life Board. There are power projects that are languishing for several years after winning the bid or the nomination for establishing the power project.

Another situation arose when the GMR Group walked away from the 555-km-long Kishangarh-Udaipur-Ahmedabad National Highway project due to delays in approval of necessary environment clearance for one of the tunnels along the highway.

... contd.

Please read our terms of use before posting comments
TERMS OF USE: The views, opinions and comments posted are your, and are not endorsed by this website. You shall be solely responsible for the comment posted here. The website reserves the right to delete, reject, or otherwise remove any views, opinions and comments posted or part thereof. You shall ensure that the comment is not inflammatory, abusive, derogatory, defamatory &/or obscene, or contain pornographic matter and/or does not constitute hate mail, or violate privacy of any person (s) or breach confidentiality or otherwise is illegal, immoral or contrary to public policy. Nor should it contain anything infringing copyright &/or intellectual property rights of any person(s).